DEA Interim Special Testing Laboratory

Owner: Drug Enforcement Administration (DEA)
Engineer: KTA Associates, P.C.
Duration: June 2000 – Dec 2000 (6 months)

This was a 30,000 sq ft tenant fit-out for the DEA temporary testing lab. DEA’s permanent facility would not be completed for two to three years. The design incorporated air-cooled chillers, air handling units, VAV boxes and gas fired heat. A DDC EMS Control System manages the entire system. The project was completed from underground acid resistant piping system to air balance and occupancy in a six-month period of time.

Competitively bid the HVAC and Plumbing Work. Assisted in the expediting and construction of the project. Worked around the clock in congested areas to complete the construction in a record time frame.

DEA Interim Special Testing LaboratoryDEA Interim Special Testing LaboratoryDEA Interim Special Testing Laboratory

Thank you for uploading.