WVU Martinsburg Periop (IPD)

Martinsburg, West Virginia

Project Overview

WVU Martinsburg is a true IPD project. Heffron teamed up with architects, engineers, WVU, a general contractor, and an electrical contractor to build a 50,000 sq ft expansion and renovation.

Heffron was brought on prior to design and worked through the design process with the team. In this model it’s a shared profit and risk situation where we are guaranteeing the project will turn out successful.

Heffron and the team spent 8 months designing and value engineering the project to hit a target budget. The team was able to reduce over four million dollars in overall cost to allow the project to move forward. The project is set to finish in 2025.

Scope of Work

01

Integrated Project Delivery (IPD) with shared profit and risk

02

Engaged prior to design alongside architects, engineers, owner, GC, and electrical contractor

03

8 months of collaborative design and value engineering to a target budget

04

50,000 sq ft perioperative expansion and renovation

Project Details

Client

WVU Medicine

Location

Martinsburg, West Virginia

Sector

Healthcare

Delivery

Integrated Project Delivery (IPD)

Size

50,000 sq ft expansion and renovation

Value Engineering

$4M+ in cost reduction